Construction Updates
Uplands is providing about $40 million in public improvements – including sewer, water, and storm drainage systems and road, traffic, and bike/pedestrian enhancements. This page will host the ongoing and upcoming construction updates, so be sure to check back often. We appreciate your patience with any inconveniences or temporary disruptions that may occur during this process.
A heartfelt thank you to the City of Westminster, Crown Pointe Academy,
and all of our dedicated attendees for sharing your time and helping make these meetings a success this year!
84th Ave (Irving to Federal)
Improvements per the PDP/ODP/Construction Documents (Water, storm drainage, roadway widening, curb, gutter, sidewalks, signal improvements)
Opened

Bradburn Drive (LaPlace to Lowell)
Improvements per the PDP/ODP/Construction Documents (Water, storm drainage, sanitary sewer, roadway widening, curb, gutter, sidewalks)
Opened
Lowell Blvd (82nd to 84th Aves)
Improvements per the PDP/ODP/Construction Documents (Water, storm drainage, sanitary sewer, roadway widening, curb, gutter, sidewalks)
Traffic Shifts – Edge Work
Present – October
84th Ave / Lowell Blvd Intersection
Traffic signals are being procured and construction will be expedited.
Fall/Winter 2025

Lowell Boulevard
(84th to 88th)
Improvements per the PDP/ODP/Construction Documents (Water, storm drainage, sanitary sewer, roadway widening, curb, gutter, sidewalks, signal improvements)
Expect Partial and Full Closures
Present – October 2025
Lowell Shaw to 88th Ave City Utility Project
Expect Full & Partial Closures
Present – December 2025
88th Ave / Lowell Blvd Intersection
Improvements requested by the City of Westminster (Water and sanitary sewer)
Full / Partial Closure
Present – October 2025

PA-A(1), PA-A(2), PA-A(3), PA-A(4), PA-A(5), and PA-(7)
Specific builder subsurface improvements through end of 2025
PA-B(1)
Home construction has started
PA-C(2)
Affordable housing development is nearing completion
Includes improvements along 88th Ave, Decatur Street, the creation of 87th Place and waterline/trail improvements in Camenisch Park.
Overall Parcel D(1)
Grading and Erosion Control expected to commence
September/October
Onsite Infrastructure is projected to start once grading is completed early 2026 and will continue into mid/end of 2027

FEMA has approved the Conditional Letter of Map Revision (CLOMR) for Uplands and Shaw Boulevard area that will significantly improve storm drainage issues in the area.
Our contractors will be commencing this construction over the next month, and we will be pushing to expedite these improvements as quickly as possible.