Construction

The team here at Uplands is anxious to begin vertical development of homes and public spaces. However, there is critical underground and horizontal infrastructure that must be built to support the new neighborhoods, retail, and commercial spaces that will make up the Uplands community. 

In total, Uplands is providing about $40 million in public improvements – including sewer, water, and storm drainage systems and road, traffic, and bike/pedestrian enhancements. 

We’re on track to receive administration approval from the city to begin construction this summer of 2023. This page will host the ongoing and upcoming construction updates, so be sure to check back often. We appreciate your patience with any inconveniences or temporary disruptions that may occur during this process.

Recent Developments:

  • FEMA has approved the Conditional Letter of Map Revision (CLOMR) for Uplands and Shaw Boulevard area that will significantly improve storm drainage issues in the area. Our contractors will be commencing this construction over the next month, and we will be pushing to expedite these improvements as quickly as possible.

Upcoming Construction

Construction Roadway Closure Update

As Uplands further advances its perimeter infrastructure improvements the following roadways are anticipated to be impacted(dates are approximate and subject to change):

    • 84th Avenue (Lowell to Irving) – Full Closure Present to October 10th
    • 84th Avenue (Irving to Federal) – Full Closure December 16nd – February 1st
    • 84th Avenue (Federal to Alcott) – Sholder Closure October 28th – February 1st
    • Bradburn Drive (La Place to Lowell) – Full Closure Present – November 5th
    • Shaw Boulevard (Circle to Lowell) – Full Closure except for local residents Present – November 12th
    • Shaw Boulevard/Lowell Intersection – Full/Partial Closure Present – October 23rd
    • 88th Avenue/Lowell Intersection (City Water and Sanitary Sewer Project) Lowell Northbound Lane 87th to 88th – November 11th to January 27th
    • Lowell Northbound Lane at Shaw – Full Closure December 16th – February 1st
    • Lowell (82nd to 84th) – Full Closure January 6 – February 1st
    • Federal Boulevard (82nd to 88th) Shoulder, Median and Utility Construction – Partial Closures September 2024 – July 2025
    • 84th Avenue (Lowell to Circle) – Full Closure except for local residents – November 11th to December 1st

Shaw Boulevard Construction Update

Construction of the storm drainage system within Shaw Boulevard will commence July 8th and is anticipated to be completed in October. The improvements will assist in reducing the flooding issues and provide a piped stormwater conveyance from the Uplands project.

The contractor will be contacting each homeowner about the construction activities, specific timing of driveway impediment and overall access of Shaw Boulevard during construction.

We appreciate your understanding as these important improvements are completed.

Summer Time Update!

  • Overall Parcel A grading is substantially complete. Minor grading and specific builder sub surface improvements may still occur through the life of the project.
  • Onsite Infrastructure(water, sanitary sewer, storm sewer, roadways) is progressing, this work will continue through this year and into 2025.
  • 88th/84th/Lowell Infrastructure Improvements have commenced and will include  closures that have been coordinated with the City.
    • This work will last through this year and into next year.
    • Lowell/84th traffic signals are being procured and construction will be expedited.
  • 88th/Lowell City Water and Sanitary Sewer Project – Uplands is assisting the City with expediting a future project of water and sanitary sewer upgrades and repairs within 88th and Lowell intersection and within Lowell from 88thto Chestnut. This project will extend some closures and other work along Lowell but is being expedited as quickly as possible to minimize impact.
  • Federal Boulevard Improvements are projected to start in September.
  • Parcel B
    • Grading and Erosion Control should be completed by early September.
    • Onsite Infrastructure should start after grading and continue into early next year.
    • Bradburn Improvements should be completed by early eSeptember.
  • Electrical and Gas improvements are being made surrounding the site and will continue throughout the year and into next year.

Questions or Concerns?